Finland has told Google to stop clearing land for two of the AI data centers in its €13 billion Finnish investment. The country's Licensing and Supervisory Authority, LVV, ordered Google's subsidiary Tuike Finland Oy to suspend major preparatory work at planned sites in Muhos and Kajaani until environmental impact assessments are finished, according to Yle News and Data Center Knowledge. Google says it "fell short" of its own standards and will comply. The order does not cancel the projects, but it is one of the clearest examples this year of permits, not power, deciding where AI infrastructure gets built.
We covered the original announcement in Google's €13B Finland nuclear and AI data center bet. This post covers what has happened since.
TL;DR table
| Question | Answer |
|---|---|
| Who ordered it | Finland's Licensing and Supervisory Authority (LVV) |
| Who is targeted | Google's subsidiary Tuike Finland Oy |
| Sites | Muhos and Kajaani (Kajaani-Otanmäki) |
| What must stop | Tree and topsoil removal, excavation, blasting, crushing, earthmoving, drainage, site roads and storage areas |
| What can continue | Planning, measurements, soil surveys and other limited or reversible work |
| Deadline | Immediately and no later than October 23, 2026 |
| How long | Until environmental impact assessments are complete |
| Area reported | About 330 hectares at Muhos, just under 200 at Kajaani-Otanmäki (Tuike's own report) |
| Google's response | Says it did not meet its own high standards, will comply; says it followed the Forest Act |
| Police | Preliminary investigation reported at Muhos |
Update (October 29, 2026): an older Hamina logging case resurfaces
Finnish public broadcaster Yle reported that documents obtained by Helsingin Sanomat through a freedom-of-information request show Tuike Finland, Google's Finnish subsidiary, felled trees without a permit on about 1.3 hectares in the Summa area of Hamina in 2018 and 2019. The logging destroyed flying squirrel corridors, feeding areas and nesting trees, and exceeded what the company had declared in its permit application.
Authorities determined in 2020 that the company was not allowed to destroy the habitat, and work stopped. At the time the logging was judged inadvertent and no crime report was filed. The regional agency's nature conservation manager told Yle the threshold for requesting an investigation has since been lowered under the new Nature Conservation Act, so a report would likely be filed today. The Association for Nature Conservation said it intends to request a police investigation. Google told Svenska Yle its current Hamina operations do not affect flying squirrel habitat.
This is separate from the Muhos matter above, where Yle reports that police have opened a preliminary investigation. No charges have been reported in either case.
Update (October 23, 2026): viral numbers versus confirmed ones
The story has spread on social media with bigger figures than the official record supports. Posts circulating on October 22 and 23 say Google felled "roughly 400,000 trees," that "wolves are roaming into Finnish villages," and that more than 93,000 Finns have signed a petition for stricter rules and a developer fee for host communities. Others say the felling was "illegal" and that Google apologized and will replant 130 hectares.
Here is what we could confirm and what we could not:
- Confirmed: the LVV order told Tuike Finland to suspend preparatory work by October 23, and a Google spokesman acknowledged the company's shortcomings and said it would follow LVV's guidance, per Al Jazeera, citing AFP and Reuters. The same report says Google spoke of tree planting across 130 hectares at Muhos as part of landscaping and biodiversity plans. That is a plan Google described, not a new compensation pledge sized to the felled area.
- Disputed: "illegal" is the question LVV is investigating: whether Tuike Finland cleared hundreds of hectares without a mandatory environmental impact assessment. Al Jazeera quotes a conservation group describing a deforested area of more than 300 hectares.
- Not found in the reports we could open: the 400,000-tree figure, the wolf sightings and the 93,000-signature petition. Treat the viral figures as unverified until a Finnish outlet, a petition platform page or LVV confirms them.
If you want to check yourself, read the LVV announcement, Tuike Finland's report to the agency, and the petition page directly, and compare hectares rather than tree counts, since hectares are what the legal threshold uses.
Timeline of what is known
- September 2026: Google announces the €13 billion Finland investment: new data centers in Muhos, Kajaani and Vaala and an expansion of Hamina.
- September 18: LVV sends a request for information to Tuike Finland, the Municipality of Muhos, the City of Kajaani and local building-control authorities (per Data Center Knowledge).
- October 2: A private individual files a request with police about the Muhos work; Iltalehti reports on October 7 that police opened a preliminary investigation (per Yle).
- By October 8: LVV's suspension order is public (Yle and Data Center Knowledge both reported it that day). Yle says LVV's concern is that the preparatory work could "significantly alter the environment."
- October 14: Deadline for Tuike to explain in writing whether it will comply.
- October 23: Latest date for the suspension to be in effect.
Why was the work halted?
The core issue is sequencing. An environmental impact assessment (EIA) is meant to collect information about a project's effects before decisions are made, including impacts, alternatives and mitigation. LVV's position, as reported by Data Center Knowledge, is that letting major site work continue could undermine that process by limiting the ability to identify impacts, examine alternatives and prevent harm. The EIA reports for the two projects are expected to be completed in 2026.
Tiina Paloniitty, associate professor of environmental and sustainability law at the University of Helsinki, told Data Center Knowledge that compliance with forestry rules does not satisfy the separate EIA requirement, and that "good faith is not a legally relevant argument here." She also called the intervention "highly unusual" and said she could not recall one at this scale. These are one academic's views based on public information, not a legal finding.
What Google says
Google's position, as quoted by Data Center Knowledge and Yle:
- It acted in good faith under Finland's Forest Act, ran nature surveys and protected environmentally valuable areas.
- Communications manager Sondre Ronander said "we did not meet the high standards we set ourselves" and that Google understands the concern.
- It intends to fully comply with the LVV order.
- It is advancing landscaping and biodiversity plans, including tree planting across 130 hectares at Muhos. Paloniitty's reply: new trees do not replace a full-grown forest.
The "illegal logging" framing seen in headlines comes from public suspicions and the police request. LVV's order rests on the EIA Act, and no court or authority has so far found a crime.
Cooling tower linked by a green power line to a data hall, illustrating Google's Finland data center sites
Power was solved, permits were not
The most useful point for infrastructure watchers comes from HyperFrame Research's Stephen Sopko, quoted by Data Center Knowledge: Google had already solved power, since Fingrid said the northern grid had room. The failure, in his view, was treating forest clearance as preparatory when Finnish law treats permanent conversion above 200 hectares as the action regulators judge. "You can often do surveys and reversible site work ahead of the permit," he said. "What you can't do is clear 300 hectares and call it anticipation."
That fits a wider pattern in our coverage: AI data centers are meeting resistance from several directions at once, including Amazon's contested site in Thane, India, San Francisco's moratorium, New York's data center moratorium debate and a Senate investigation into hyperscaler cost claims. Google has also been under pressure over secrecy with local officials.
How an environmental impact assessment is supposed to work
Because the dispute is about order of operations, it helps to spell out what an EIA procedure is for. In plain terms it is a structured review that runs before a large project is approved. The developer describes the project, the authorities and the public comment, and a reasoned conclusion is produced that decision-makers must take into account. Three functions matter here, all drawn from the way Data Center Knowledge and Dr. Paloniitty describe the process:
- Identifying impacts. The review catalogs what the project will do to land, water, wildlife and neighbors. That requires the land to still be in something like its original state.
- Weighing alternatives. A site layout, a different location or a smaller footprint can only be compared if nothing irreversible has happened yet.
- Deciding on mitigation. Measures to reduce harm are chosen using the findings. Replanting after clearing is a remedy, but it is not the same as choosing not to clear.
If a developer fells and grades hundreds of hectares first, the assessment becomes a description of what was already done. That is the reasoning LVV reportedly gave when it said continued work could undermine the process. It is also why the legal scholar quoted by Data Center Knowledge argued that planting trees on 130 hectares does not cure the problem.
Preparatory work versus permanent change
The allowed and banned lists in the order show where the line is drawn:
| Allowed to continue | Ordered to stop |
|---|---|
| Planning and design | Tree removal |
| Measurements | Topsoil removal |
| Soil surveys | Excavation, blasting and crushing |
| Other limited or reversible activities | Earthmoving and drainage changes |
| Building site roads and storage areas |
The distinction is reversibility. A soil sample can be taken and forgotten; a felled forest cannot be undone on a project timeline. Operators building AI campuses at speed, where each month of delay is a month of idle capital, face a real temptation to treat early earthworks as harmless. The Finnish case suggests regulators are now willing to draw the line firmly.
Is this specific to Finland?
Not entirely. Environmental assessment sequencing exists in many jurisdictions, including across the EU, and large facilities everywhere face the same question of what counts as "preparatory." What is distinctive here is the scale of the investment and the public nature of the intervention. The €13 billion figure is Google's own announced investment across four Finnish locations, and Finland had been marketing its cold climate, clean power and spare grid capacity to exactly this kind of builder. Our earlier post on Google's Finland bet explains why those sites were attractive; this order shows the permitting side of the same bargain.
What happens next
Per Data Center Knowledge, LVV is initially seeking voluntary compliance. If Tuike does not comply, the agency said it will consider a formal enforcement procedure that could be backed by a conditional fine. Planning and survey work can continue, so the timeline slip depends on how fast the assessments finish. Open questions:
- Whether Tuike confirmed compliance by its October 14 deadline, and what LVV said in response. We could not find a published answer.
- Whether police move from a preliminary review to a pre-trial investigation at Muhos.
- Whether the Kajaani and Hamina sites face further scrutiny. Yle's own site also lists an October 20 report that a Google subsidiary cut down flying-squirrel habitat in Hamina, which we have not independently reviewed.
- How the delay affects Google's Finnish AI capacity plans.
What this means for people building on or around AI infrastructure
- Capacity announcements are not capacity. A headline investment figure says nothing about when a site can be built. Permit and assessment sequencing can add months.
- Power access is only one gate. Google's grid access did not prevent a halt.
- Expect more scrutiny of site prep. Regulators and local campaigners are watching clearing and earthworks, not just the final building.
- Plan for regional diversification. Teams that depend on a single region's AI capacity should keep alternatives, a point we also made in our California data center bills coverage.
Related reading
-
Google commits $15 billion to Malaysia data centers for 2027 and 2028
-
Google bets €13B on Finland: nuclear power meets AI data centers
Details come from Yle News and Data Center Knowledge reports of October 8, 2026 and may change as the case develops.
